| MCI/WorldCom
Tulsa, Oklahoma
- This project consisted of over
35,000sf of raised floor containing computer facilities,
telephone switch, and telecommunication equipment.
- In addition, it included 8700sf
of Network and Switch Control Center facilities which
monitor and control the entire WorldCom network.
- Major equipment included a 1400kW
emergency generator, 800kVA multi-module redundant
UPS, 310T of air-conditioning, and complete preaction
system.
- Additional UPS and Emergency
Generation now provide a total UPS capacity of two
separate 1500kVA multi-module redundant systems configured
in a separated output dual power cord configuration.
- This concept was developed following
a reliability evaluation of various alternatives.
- The total emergency generator
facility involves four 1750kVA parallel generators.
- The Module 1-4 Project involved
the conversion of over 500,000sf of space to primarily
office use. Other aspects of the project included
27,000sf of computer facility/control center, cafeteria,
and call center.
- The Module 5 project included
a new four story building with 240,000sf of space
consisting primarily of general office space. The
building also includes 2,000sf computer room, fitness
center, adjacent cafeteria, and 500 person call center.
Phillips & Bacon also designed the base building systems.